March 2019 Progress Photos

Top layer of asphalt pavement removed, revealing concrete pavement
The top layer of asphalt pavement is removed from northbound U.S. 1 in the first step of reconstruction the highway. The original concrete pavement under the overlay will be removed next.

Temporary intersection at U.S. 1 and Street Road
Eastbound Street Road (Route 132) traffic at the temporary intersection providing access to and from northbound U.S. 1.

Crews removing the guiderail on U.S. 1
A crew removes the guiderail that separated the on and off ramps for the eastbound Street Road (Route 132)/U.S. 1 Interchange. The ramps are being rebuilt as part of northbound construction on U.S. 1.

New northbound traffic pattern on U.S. 1
New northbound traffic pattern, with the right turn lane for continued access to businesses.

New northbound traffic pattern on U.S. 1
New northbound traffic pattern, with the right turn lane for continued access to businesses.