Based on our current level of progress with the Environmental Assessment (EA), we will continue to develop the EA document through the summer and publish it this fall.
We anticipate an environmental decision in the summer of 2026, which, at that time, assuming it’s a finding of no significant impact, we would shift into the final design/right-of-way acquisition phase of the project.
We anticipate that to start early in 2027. We anticipate that phase to take 18 to 24 months, which would put us in 2029 for a construction start. The construction is anticipated to take 3 construction seasons or 3 years. Details on the construction schedule will become available closer to the construction start date.